The workflow in question consists of 4 jobs. Each job ends with assign status step (ok, steps, one for success and one for failure). The last thing that gets executed in a workflow is an assign status step! Still nothing...
I even tried the following. I deleted the build-life that was showing at the dashboard. It went into Inactive state (which I don't understand at all, because when I delete other build-lifes, they are gone!) and it's still showing in the dashboard.
Currenty, the dashboard is totally useless because it shows statuses as they were 2 months ago...
Mladen
-----Original Message-----
From: anthill-pro-bounces at lists.urbancode.com [mailto:anthill-pro-bounces at lists.urbancode.com] On Behalf Of Ryan Smith
Sent: Monday, January 14, 2008 4:53 PM
To: AnthillPro user and support list.
Subject: Re: [Anthill-pro] Question about the new dashboard
Mladen,
The workflow dashboard should show the most recent build lives that have been assigned each build life status. A build life will not appear in here because its workflow succeeds or fails. It only appears if you assign a build life status to it with the assign status step.
It sounds like you had a secondary workflow fail on a build life and are expected that to set a build life status of failed. Usually the success and failed build life statuses are only assigned on the originating workflow.
Ryan
Mladen Maravić wrote:
> Well, I have a project (lets call it Project A) that has a life cycle
> model called Life-Cycle Model M. This LCM M has the default statuses
> (Archived, success, failure). My stamping strategy just pust a timestamp
> for the stamp (it's a nighty build).This all works well! The difference
> is in the data I get when I view them at two different places:
>
>
>
> 1. Dashboard. I login into Anthill and I'm presented with the
> dashboard. In the dashboard I find the Project A, I expand it's
> workflow, and there is my dev.nighty workflow. Next to it is a status
> "Failed" and a Stamp "5_5-n-20071130.2203" (a build that failed that was
> run 2007-11-30; almost two months ago).
>
> 2. If I now click the workflow name I get a page that gives me (at
> the top) the "Most Recent Status Assignments" list. This list contains
> the following:
>
>
>
> · Status: "success" Build life: "1549" Stamp:
> "HEAD-n-20080114.0835"
>
> · Status: "failure" Build life: "1453" Stamp:
> "HEAD-n-20080102.2204"
>
>
>
> So, what's the deal with the dashboard? It is clearly NOT showing the
> most recent status. It makes no sense...
>
>
>
>
>
>
>
> *From:* anthill-pro-bounces at lists.urbancode.com
> [mailto:anthill-pro-bounces at lists.urbancode.com] *On Behalf Of *Steve Boone
> *Sent:* Thursday, January 10, 2008 5:31 PM
> *To:* AnthillPro user and support list.
> *Subject:* Re: [Anthill-pro] Question about the new dashboard
>
>
>
> Mladen,
>
> Those status and stamps come from the Lie-Cycle Model that is associated
> with a project. When you create a project, you must specify a
> Life-Cycle Model. Life-Cycle models are created from the System Tab.
>
> Stamping is done differently in 3.4, and uses Project Properties to
> create the stamp.
>
> Also, can you take a look at your stamping strategy on your workflow and
> let me know what is there?
>
> Regards,
> Steve Boone
>
> On 1/10/08, *Mladen Maravić* <mladen.maravic at svgroup.hr
> <mailto:mladen.maravic at svgroup.hr>> wrote:
>
> After upgrading to 3.4 we got a brand new dashboard that shows me all of
> my active projects, project's workflows and it's statuses and stamps.
>
>
>
> Here is the question: where does Anthill take those statuses and stamps
> from?
>
>
>
> For example,
>
> I have a project called RetailServices. It consists of several
> workflows. One of them is "nightly". The "nightly" workflow, as I look
> at it through Dashboard, has a status of failed and a stamp from almost
> a month ago. If I click on the workflow name, I get a more detailed page
> that tells me that the most recent "nightly" build was a success and was
> carried out half an hour ago and requested by me. So why does dashboard
> say that the "nightly" workflow has failed and puts a month-old stamp on
> the page instead of the half-an-hour-ago one? This is true of almost all
> of my workflows! The dashboard simply doesn't reflect the most current
> status of my workflow builds, but rather some past status that seems
> totally random. Can anybody shed some light on this?
>
>
>
>
>
> svgroup_mail
>
> MLADEN MARAVIĆ
>
> V. RAVNICE 15, HR-10000 ZAGREB, CROATIA
>
> *PHONE:* +385 1 2958 747
>
> *FAX:* +385 1 2989 324
>
> *GSM:* +385 91 3841 397
>
> mladen.maravic at svgroup.hr <mailto:mladen.maravic at svgroup.hr>
>
> www.svgroup.hr <http://www.svgroup.hr/>
>
>
>
>
> _______________________________________________
> Anthill-pro mailing list
> Anthill-pro at lists.urbancode.com <mailto:Anthill-pro at lists.urbancode.com>
> http://lists.urbancode.com/mailman/listinfo/anthill-pro
>
>
>
>
> ------------------------------------------------------------------------
>
> _______________________________________________
> Anthill-pro mailing list
> Anthill-pro at lists.urbancode.com
> http://lists.urbancode.com/mailman/listinfo/anthill-pro
--
===========================================================
Ryan Smith. 2044 Euclid Ave., Suite 600
Lead Developer Cleveland, Ohio 44115
Urbancode, Inc.
email: rws at urbancode.com
web: www.urbancode.com phone: 216-858-9000
web: www.anthillpro.com fax: 216-858-9602
===========================================================
_______________________________________________
Anthill-pro mailing list
Anthill-pro at lists.urbancode.com
http://lists.urbancode.com/mailman/listinfo/anthill-pro
More information about the Anthill-pro
mailing list