I was trying to run parallel jobs and I seem to be having problems with
${bsh:WorkspaceVersion.get()}
I have a job which just does the stamp and then gives control to 2 other
jobs that run in parallel. The parallel jobs need to get the workspace
version however, the above script never executes. In fact, it just
leaves the script as is.. Any reason why it would do this?
The jobs use a shell script builder step and the command line contains
something as simple as
./build.sh -Dversion=${bsh:WorkspaceVersion.get()} deploy